December 22, 2025

Upper Mill Creek Road Improvement Project Construction Update

As we wrap up the year, we're taking a moment to look back on everything accomplished on the Upper Mill Creek Canyon Road Improvement Project, and there's a lot to celebrate!

  • Construction is now about 50 percent complete
  • Crews made major progress across the entire corridor before pausing for winter
  • Every large culvert (the drainage channels that carry water under the road) is finished except White Bridge, which is now halfway built. 
  • Road grading has reached the halfway point as well, extending up to Culvert 10139.
  • The soil nail walls are structurally complete, with their decorative finish coming next year.
  • Alexander Parking Lot has been fully graded with most of the new rock wall set in place.
  • Roughly 25 percent of the new drainage pipes are installed
  • 75 percent of the rock stream embankments are now in place to protect the canyon's waterways.

Thank you to our project partners, contractors, and canyon users for your patience and support throughout such a big construction year.

We're excited for everything ahead in 2026 and grateful for the momentum we're carrying into next season.